Construction safety plans

A construction safety plan can assist principal contractors to manage their workplace health and safety obligations.

A principal contractor must prepare a construction safety plan before construction work starts.

The plan must state:

The plan must be written so it is easy to understand, signed and dated by the principal contractor. It must be available for the length of the project.

The principal contractor must sign and date work method statements that have been received and keep them with the plan, as well as monitor their implementation.

The principal contractor cannot allow work to start unless:

The plan must be amended if there are changes in how risks will be managed. The principal contractor must inform any affected person of the change.